Ooltewah Construction Notice

There is going to be a 2-phase concrete construction project in the back 40 (to the left of the Small Wrecker Shipping racks) extending to gate 4 (near Country Village Drive).  This project will begin Monday, July 17th, and is scheduled to be completed in the next four weeks, weather permitting.

Phase 1 is starting TODAY, Monday, 7/17/2023, and is scheduled to be completed on Monday, 7/31/2023.  Stay tuned for more updates throughout the duration of this project.  Please see the above image for a visual aid on the phases 1 and 2 layout.  Maintenance will put cones out for temporary traffic flow.

Thank you for your patience and understanding, as we re-route ALL traffic and material through the next four weeks.

If you have any questions, please contact Chris McGill, Todd Berghoff, or Tim Roth.